About  Project

Electrification of Potshini Phase 2 115 connections.

MV Scope of work 

  • Supply and install 3×32 kVA new transformers at 11kV supply.
  • Supply and install 6×64 kVA new transformers at 11kV supply.

LV Scope of Work

  • Build 0.4km of single phase 35mm^2 ABC XLPE LV conductor for the whole project.
  • Build 5.5km of dual phase 35mm^2 ABC XLPE LV conductor for the whole project
  • Build 10.3km of single phase 70mm^2 ABC XLPE LV conductor for the whole project
  • Supply and install 4.8km of 6mm^2 Airdac in total for 41 connections.
  • Supply and install 115 x smart split meters.
ClientOkhahlamba Local Municipality
Project Duration4 Months